Phase 1 of the study is complete and assessed the multimodal transportation needs of the five-county region.
Phase 2 will prioritize the identified transportation needs and develop strategies to address them. Phase Two is currently underway and is expected to last 18 months.
| Identify Projects | Winter 2011 |
| Evaluation Criteria | Winter/Spring 2011 |
| Strategies "Toolbox" | Winter/Spring/Summer 2011 |
| Alternative Finance | Winter/Spring 2011 |
| Corridor Analysis | Summer/Fall 2011 |
| Prioritization | Winter 2011 |
| Joint Stakeholder Advisory Panel/ Corridor Strategies Working Group meeting |
Spring 2012 |
| Public Officials Briefing | Spring 2012 |
| County Chairs Update | Spring 2012 |
| Draft Report Presented | Late Spring 2012 |
| Phase 2 Report Complete | Early Summer 2012 |