Phase 1 of the study is complete and assessed the multimodal transportation needs of the five-county region.

Phase 2 will prioritize the identified transportation needs and develop strategies to address them. Phase Two is currently underway and is expected to last 18 months.

Phase 2

Identify Projects Winter 2011
Evaluation Criteria Winter/Spring 2011
Strategies "Toolbox" Winter/Spring/Summer 2011
Alternative Finance Winter/Spring 2011
Corridor Analysis Summer/Fall 2011
Prioritization Winter 2011
Joint Stakeholder Advisory Panel/
Corridor Strategies Working Group meeting
Spring 2012
Public Officials Briefing Spring 2012
County Chairs Update Spring 2012
Draft Report Presented Late Spring 2012
Phase 2 Report Complete Early Summer 2012